|
MOISTURE TESTING OF CONCRETE SUB FLOORS
Concrete
sub floors should always be tested for moisture content before
commencing floor preparation or installation of new floor coverings.
Testing should not be restricted to the ground floor but to all
levels of a building where floor coverings are to be installed
because the subfloor may have an unacceptable moisture level or
be "wet" because moisture has "wicked" up
piers, columns or walls.
A
concrete sub floors may be "wet" because:
- It
is a new slab and the water used in the mix to allow the concrete
to be pumped and troweled has not fully evaporated to the
atmosphere or been converted to help cure the concrete.
- It
may also be a slab without a plastic moisture membrane which
may allow moisture in
the ground to penetrate the slab and allow its moisture content
to rise and be above the recommended level.
Australian
Standard AS1884-1985 Floor Coverings- Resilient Sheet and Tiles
Laying and Maintenance Practices, sets out the methods of testing
for sub floor moisture and the acceptable levels. Copies of this
document may be purchased from the Standards Association Of Australia
in your capital city.
As
a "rule of thumb", its has been found that under average
conditions with good ventilation, a 100 mm thick slab of normal
concrete, drying from one face only will take approximately five
months to dry to a moisture level to allow floorcoverings to be
installed. The application of a vapour barrier or water based
epoxy moisture barrier will reduce the waiting time before
installation can commence.
A
concrete sub floor can be accurately checked to determine its
moisture content using an Hair Hygrometer Test or an Electrical
Resistance Meter.
- An
Hair Hygrometer Test
Meter involves
the use of an accurately calibrated meter which calculates the
humidity level in a sealed area and the level may be read from
the dial on the instrument. The Hygrometer is laid on the concrete
sub floor and sealed to the slab for at least 16 hours allowing
it to determine the amount of moisture vapour being omitted
by the slab.
- An
Electrical Resistance Meter determines the resistance
in the slab to the flow of electricity and is calibrated to
determine the percentage of moisture content and the results
are shown on the instrument dial as the moisture level contained
in the slab. The test is carried out by driving two nails into
the slab approximately 100mm apart and then placing two probes
in contact with the nails and immediately being able to read
the percentage of moisture contained in the slab. The Electrical
Resistance Meter test is the method most often used because
a moisture content reading is quickly available.
An
Acceptable Sub-floor
Australian
Standard 1884-1985 Appendix A.5.3 states that a sub floor is not
sufficiently dry if the moisture content exceeds 5.5 percent.
A concrete sub floor must comply with the relevant Australian
Standards before commencement of the application of floor preparation
materials such as cementitious compounds, primers, adhesives or
floorcoverings because the installation may fail. The failure
may result in the floor preparation materials or the floor coverings
bubbling severely which may cause a possible tripping or safety
issue or be unsightly requiring expensive repairs or replacement.
Further
information on
floor coatings, sub floor preparation and sealers may be obtained
from our information folder "Floor Coatings" or
At : www.rlapolymer.com.au
Contact us at: info@rlapolymers.com.au
Issued:
September 2004
|