MOISTURE
TESTING OF CONCRETE SUB FLOORS
Concrete
sub floors should always be tested for moisture content before commencing
floor preparation or installation of new floor coverings. Testing should
not be restricted to the ground floor but to all levels of a building
where floor coverings are to be installed because the subfloor may have
an unacceptable moisture level or be "wet" because moisture
has "wicked" up piers, columns or walls.
A
concrete sub floors may be "wet" because:
- It
is a new slab and the water used in the mix to allow the concrete
to be pumped and troweled has not fully evaporated to the atmosphere
or been converted to help cure the concrete.
- It
may also be a slab without a plastic moisture membrane which may
allow moisture in
the ground to penetrate the slab and allow its moisture content
to rise and be above the recommended level.
Australian
Standard AS1884-1985 Floor Coverings- Resilient Sheet and Tiles Laying
and Maintenance Practices, sets out the methods of testing for sub floor
moisture and the acceptable levels. Copies of this document may be purchased
from the Standards Association Of Australia in your capital city.
As
a "rule of thumb", its has been found that under average conditions
with good ventilation, a 100 mm thick slab of normal concrete, drying
from one face only will take approximately five months to dry to a moisture
level to allow floorcoverings to be installed. The application of a
vapour barrier or water based epoxy moisture barrier will reduce the
waiting time before
installation can commence.
A
concrete sub floor can be accurately checked to determine its moisture
content using an Hair Hygrometer Test or an Electrical Resistance Meter.
- An
Hair Hygrometer Test
Meter involves
the use of an accurately calibrated meter which calculates the humidity
level in a sealed area and the level may be read from the dial on
the instrument. The Hygrometer is laid on the concrete sub floor and
sealed to the slab for at least 16 hours allowing it to determine
the amount of moisture vapour being omitted by the slab.
- An
Electrical Resistance Meter determines the resistance
in the slab to the flow of electricity and is calibrated to determine
the percentage of moisture content and the results are shown on the
instrument dial as the moisture level contained in the slab. The test
is carried out by driving two nails into the slab approximately 100mm
apart and then placing two probes in contact with the nails and immediately
being able to read the percentage of moisture contained in the slab.
The Electrical Resistance Meter test is the method most often used
because a moisture content reading is quickly available.
An
Acceptable Sub-floor
Australian
Standard 1884-1985 Appendix A.5.3 states that a sub floor is not sufficiently
dry if the moisture content exceeds 5.5 percent. A concrete sub floor
must comply with the relevant Australian Standards before commencement
of the application of floor preparation materials such as cementitious
compounds, primers, adhesives or floorcoverings because the installation
may fail. The failure may result in the floor preparation materials
or the floor coverings bubbling severely which may cause a possible
tripping or safety issue or be unsightly requiring expensive repairs
or replacement.
Further
information on
floor coatings, sub floor preparation and sealers may be obtained from
our information folder "Floor Coatings" or
At : www.rlapolymer.com.au
Contact us at: info@rlapolymers.com.au
Issued:
September 2004
Top